Supply of drinking water for the population between Bata and Senje from Km 6

Supply of drinking water for the population between Bata and Senje from Km 6


Project Description
  • 11 June 2018
Mission Description
  • Inspection study and execution drawingsSite work inspection
  • Studies and work technical assistance
  • Financial supervision
  • Preparation of monthly reports and technical monitoring
  • Control and validation of payment situations
  • Scheduling of payments
Projet Description

Control of the following projects:

  • Setting up on 34 Km of a DN200 (PN 10) PE pipe with online equipment
  • Construction of a treated water pressure stations at Bata with equipment
  • Construction of water course crossing structures
  • Construction of delivery tanks, 10 tanks of 5 m³ and 5 tanks of 10 m³